Value $ 6,500.00

Project Description:

VBS carried out these works on the same day after numerous attempts to repair by previous builders.

Remove bi-fold door unit and store onsite for re-installation on completion of rectification once repairs have been carried out.

Work Included:

  • To remove existing trims and associated sill timbers to bi-fold door system.
  • Apply sub sill flashing and or polyurethane membrane system.
  • Re configure concrete hob.
  • Replace reveal to timber internal door track inclusive of router channel.
  • Apply external and internal trims.

Water tested window to confirm all leaks had been rectified.

Refer to testimonial from owner Henry at Birchgrove